SYMPTOMS

After a resource updates a task in Project Web Access and submits the update, the task update is submitted to a project manager other than the designated status manager.

RESOLUTION

To resolve this issue, apply hotfix 956060. For more information, click the following article number to view the article in the Microsoft Knowledge Base:

956060  (/Feedback.aspx?kbNumber=956060/ ) Description of the Project 2007 hotfix package (Project.msp): August 26, 2008

APPLIES TO
  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Standard 2007
Keywords: 
kbqfe kbexpertisebeginner kbsurveynew kbprb KB956712

 

Microsoft Knowledge Base Article

This article contents is Microsoft Copyrighted material.
Microsoft Corporation. All rights reserved. Terms of Use | Trademarks


You can follow any responses to this entry through the RSS 2.0 feed. You can leave a response, or trackback from your own site.

AddThis Social Bookmark Button

Leave a Reply

*
To prove that you're not a bot, enter this code
Anti-Spam Image